Tustin Unified School District

Tustin Unified School District

Client:

Tustin Unified School District

Project Name/Assignment:

District-Wide Classroom Learning Technology

Challenges:

  • Extremely fast track project requiring approximately 900 classrooms to be completed within 120 calendar days.
  • DNG was tasked with developing a pre-installation process to reduce field time and increase efficiencies. The considerations had to include a methodology to assemble, configure, test and identify all system elements in advance of the classroom installation which saved hundreds of hours of field installation time and kept the project on schedule.

Solutions:

DNG’s training academy was able to train technicians on specific tasks which reduced manpower requirements, minimized installation errors, increased efficiencies, and enabled DNG to complete this massive project on-time.

Project Features

  • Collaborative and Digital Learning Classrooms
  • Video Conferencing and Virtual Meetings
  • Conference Rooms and Presentation Systems
  • Live Streaming, Digital Signage and Wireless Systems
  • Campus Safety and Video Surveillance
  • Interactive Conference and Meeting Rooms

Noteworthy:

It was DNG’s solid financial infrastructure which capitalized the equipment and manpower needed to complete this $5MM project, and also fulfilled the customer’s bonding requirements. It also provided the customer with a single company capable of completing this project on-time and without significant change orders.